Workers Compensation Beneficiary Challenges to ERISA Setoff Allowed

A US District Court has held that a workers’ compensation claimant is allowed to go forward with his challenge of a delayed setoff of workers’ compensation benefits. The ERISA plan administrator originally, in October 2004 determined that no offset of workers’ compensation benefits would be permitted based upon a specific loss date. In December 2007 the beneficiary was by the plan administrator that the date offset had been changed and that an offset would be required.

The injured worker instituted the action claim that the plan was estopped by the late chance of plan determination of the disability date.

Luppino v. Sedwick Claims Management Services, Inc., et al., Civil Action No. 08-cv-5315 (DMC-MF), 2010 WL 1999316 (D.N.J.), Slip Copy, Unpublished Opinion.